Agenda for July 18, 2022 peer review meeting.
Reply 0 0
Doug Leeper
General slides used to facilitate the July 19, 2022 meeting are attached.
Reply 0 0
Doug Leeper
Written version of comments provided by Angel Martin during the July 18, 2022 panel meeting and submitted via email after the meeting:

"Concerning the wetland-based criteria for establishing minimum wetland and lake levels meeting today, I offer the following comment.

Suggest that some language be added in the report concerning a plan 5-10 years in the future to examine available datasets and updated methodology in order to possibly improve the criteria for establishing the minimum levels. Also, suggest doing some comparison of results on a systematic basis with other methodologies applied by other Water Management Districts. This comparison could be used to determine whether varying methodologies should be applied to specific wetland ecosystems. This should also help in the transfer of technology and ideas among Districts.

Thank you for the opportunity to comment. Please contact me you need any additional information or clarification."

Reply 0 0
Doug Leeper
Per request from the Panel, attached are versions of their draft xeric and mesic review reports which include my minor, editorial comments that were discussed during the July 18, 2020 meeting.
Reply 1 0
Chris Shea
Hi. Great meeting today. I appreciate all the work that the panel and Doug have done. Here is a written version of the comment I made today:

Both the original cypress offset work done by the District and the xeric-associated wetland offset study recently completed by GPI avoided addressing significant harm directly. In the District cypress work, the grouping was done by "significant change" in parameters scored under a WAP precursor. In the xeric study, professional opinion on ecological stress was subjected to peer review, but it was not tied to any regulatory criteria or definition of adverse impact. As I stated, during the recovery assessment it was shown that the failure to meet an established metric based on stress designations often did not result in a conclusion of adverse impact in field review performed by experienced WUP permitting staff. As with hydrology, so with ecology - any detectable change in a parameter from baseline does not equate to adverse impact or significant harm. There is a level, perhaps associated with a structural change or a loss of wetland function, that is adverse and a significant harm. What is this level?

I understand the short cuts taken to date and don't necessarily disagree with them. We are building on previous studies and the hydrologic analysis done to date alone has been extensive and impressive. Why mess with the messier ecological data? The reason is twofold: that was the original charge - to identify significant harm levels, not change or stress. And the second reason is that it may well lead to more accurate and precise levels, and reduce misclassification error. For example, if some of the ecological stress characteristics associated with the xeric-associated study wetlands in the stressed group are found to be within the natural variability of xeric-associated wetlands over time, their removal could result in a different calculated offset, and different measures of variability and confidence. (I'm not saying we target wetlands in the stressed group for examination, better to start over and try to define an adverse impact level first.)

There is guidance in 40D-2 Basis of Review, Section 3.3.1.1.4 Performance Standards (for wetlands). That and an examination of the ecological data and characteristics for wetlands deemed to have an adverse impact by District regulatory staff would be a good place to start. I think we now have enough data and expertise to tackle the difficult question of quantifying (or at least describing in a way that could be consistently applied) the ecological changes and stress characteristics associated with significant harm and adverse impact

As far as this being outside the charge for the panel in terms of making a recommendation on continued work on defining significant harm in ecological terms, I'll leave that up to you all. I don't see how something so fundamental could be. In my opinion, it certainly isn't outside the continued responsibility of the District or permittees to further refine the ecological characteristics of significant ecological harm to wetlands, and not rely on surrogate measures indefinitely.
Reply 0 0
Doug Leeper

Attached is a draft summary of the July 19, 2022, peer review panel meeting.

This draft document is being posted during the period when the forum is “open” for comment, i.e., prior to 5:00 p.m. today.

The Panel is in the process of completing their final peer review reports, so a final version of this draft meeting summary may not be posted today, but will be posted by the District following concurrence from all panelists regarding the summary comments.

Reply 0 0
Jim Bays
Doug, i have no changes or edits to the July 18 meeting summary. Thank you.
Reply 0 0
Brian Ormiston
Doug, I approve of this meeting summary and have no suggested changes.  Thank you.
Reply 0 0
Doug Leeper
Final summary (DRAFT watermark removed) approved by Jim Bays, Brian Ormiston and John Emery for the July 18, 2022 peer review meeting is attached.